badget bridge 300MADISONVILLE, Ky. (11/7/13) – A contractor for the Kentucky Transportation Cabinet (KYTC) plans to close KY 1069/Stagecoach Road in Hopkins County on Friday, Saturday, and Monday, Nov. 8, 9 & 11, 2013, as part of ongoing work on the new Brown Badgett Loop Connector Bridge Project.
 
This closure on KY 1069/Stagecoach Road from 8:00 a.m. to 5:00 p.m., CST, is to allow improvements to a dip near the intersection with the new connector and allow a nearby cross drain on KY 1069 to be replaced.
 
According to KYTC District 2 Chief Engineer Kevin McClearn, the work can be completed with a daytime closure over about 3 working days.
 
“We originally thought work on the dip in KY 1069 just south of the new intersection could be completed without closing KY 1069. However, by allowing the contractor to close the road to traffic the work can be completed quicker and with a greater level of safety for both workers and the driving public,” McClearn said. “Instead of maybe a week or two of traffic disruptions, the contractor should be able to complete the work in a few days by closing KY 1069 to all traffic.”
 
Work to raise the dip in the roadway is to provide better sight-distance at the new intersection.
 
“During the design of the project, engineers carefully examined the dip in KY 1069 near the intersection. An analysis determined that an acceptable line of sight existed. However, as the new intersection started to take shape, we determined that additional improvements were warranted,” McClearn Said. “By taking some time to raise a small portion of the roadway in the low spot we can provide an additional margin of safety at this location.”
 
While the roadway is closed for the extra work near the intersection, it made sense to include replacement of a nearby cross drain that had some issues.
 
“The cross drain is a maintenance issue that needs to be addressed, and with the temporary closure of the roadway, it is a good opportunity to safely make those repairs with no additional inconvenience to traffic,” McClearn said.
 
The closure on KY 1069/Stagecoach Road is at mile point 1.632 between Robert Lane and J.D. Buchanan Road. Message boards have been placed at the site to alert motorists to the planned closure.
 
Work on the New Brown Badgett Loop Connector Overpass started April 8. The new structure will serve as an extra entrance point to Madisonville North Hopkins High School from KY 1069/Stagecoach Road. It replaces a wooden structure that was closed to traffic in October 2007. The new concrete bridge will be able to handle school bus traffic, which was unable cross the old structure...
 
Alignment of the new structure pulls off of Stagecoach Road north of the existing bridge. The new bridge crosses the railroad tracks at an angle and ties into Brown Badgett Loop south of the old bridge location. Much of the remaining work at the site involves construction of the connector road and a new connecting point to KY 1069, as well as connecting Brown Badgett Loop to the new bridge.
 
Once the work is completed on KY 1069, the contractor will allow the reworked areas to settle for about a week before applying a finish coat of asphalt. McClearn says he’s optimistic the new bridge and connector can be ready for traffic around December 1st.

Jim Smith Contracting Company, LLC, is the prime contractor on the $1.8 million project.
 
SurfKY News
Information provided by Keith Todd, KYTC

LIKE SurfKY on Facebook - Click here to LIKE us now.

© Copyright 2015 SurfKY News Group, Inc. All rights reserved. This material may not be published, broadcast, or rewritten without permission. SurfKY News encourages you to share this story on social media.

In Other News...

OPR Accepting Applications for Summer Day Camps

OWENSBORO, Ky. (4/16/15) — Owensboro Parks and Recreation is now accepting registrations for their two amazing Summer… Read More

Children's Advocacy Benefit Rally on Target for Tomorrow

OWENSBORO, Ky. (4/17/15) — The Owensboro Police Department is pleased to announce the third annual Children’s Advocacy… Read More

Most Read This Week

April 13, 2015 6122

Three Juveniles, Adult Accused of Vandalizing…

by Deputy Will Coursey
April 14, 2015 4689

Several Juveniles Charged in Connection with Fight

by SurfKY News
April 09, 2015 3894

MPD, HCSO Joint Investigation Leads to Two…

by Lt. William Poe
April 16, 2015 3295

Crime Stoppers Fugitive of the Week – April 16,…

by Hopkinsville – Christian County Crime Stoppers
April 09, 2015 3115

Woman Charged with Multiple Offenses Including…

by Madisonville Police Department

Most Read This Month

March 18, 2015 10025

UPDATE: Hanson Man Located in Henderson, Taken to…

by Trooper Stu Recke
April 02, 2015 8413

UPDATE: Madisonville Man Injured in Head-on…

by Doreen Dennis, SurfKY News

Stories Trending Now

April 16, 2015 3295

Crime Stoppers Fugitive of the Week – April 16,…

by Hopkinsville – Christian County Crime Stoppers
April 16, 2015 1927

Dawson Native, Former Disney Graphic Designer…

by Amber Averitt, SurfKY News
April 17, 2015 1480

An Open Letter from an Addict

by Olivia Kirks
April 16, 2015 1316

Madisonville Police Arrest Reports Released -…

by SurfKY News
April 16, 2015 1316

Hopkins County Health Department Food Scores Thru…

by Barry Franklin
April 16, 2015 1149

Muhlenberg District Court Fines Handed Down

by Charles W. Riley II, SurfKY News
April 16, 2015 1141

Hopkins County Sheriff's Reports Released

by SurfKY News
April 16, 2015 1017

Business Spotlight: Community Health Centers…

by Charles W. Riley II, SurfKY News
April 16, 2015 890

Children’s Advocacy Director Shares Information…

by Amber Averitt, SurfKY News
April 16, 2015 780

Kentucky's Jobless Rate Dips to 5.1 Percent in…

by Kim Brannock