ky state TN bridge 300PADUCAH, Ky. (3/19/13) – The contractor for the new U.S. 60 Tennessee River Bridge at Ledbetter had mixed news for the Kentucky Transportation Cabinet (KYTC) this week.
KYTC District 1 Chief Engineer Jim LeFevre says while the new bridge is still on track to open well ahead of the original schedule, it will not likely be ready for two-lane traffic in May or June.
“The more likely time frame for opening the bridge is mid-summer,” LeFevre said. “Our contractor continues to be committed to getting traffic on the new bridge as quickly as possible. Workers have already starting placing forms to prepare for pouring a deck on the main truss span.”
The updated timetable came in the form of a regular progress report from the contractor. LeFevre noted that while work is ahead of schedule on the approach spans, progress on the main truss has been slowed by weather and delays in shipments of steel from mills and fabricators in Minnesota and Wisconsin.
In May 2012, transportation officials negotiated a $3.8 million incentive package with the contractor, Kay & Kay/Haydon Brothers. The goal was to get the new bridge opened at least to two-way traffic as much as 14 months ahead of schedule to help alleviate traffic restrictions caused by a 3-ton load limit on the existing bridge.
Starting May 1, the state will deduct $19,000 per day from the incentive fund until two-lane traffic is established. If traffic is not running on the new bridge by Sept. 1, the contractor will not receive incentive money.
LeFevre says the new bridge is still likely to be open to two-lane traffic almost a year ahead of the original schedule.
“We’re still on track to get two-lane traffic moving over to the new bridge in mid-summer,” LeFevre said. “That is our ultimate goal, to restore full connectivity for residents of McCracken County and Livingston County that has been disrupted by the 3-ton load limit on the existing bridge.”
Even with a mid-summer opening, the contractor can still claim a portion of the $3.8 million in incentives by cutting almost a year off the original July 2014 opening date.
Some of the time saved on the project comes from placing 2-lane traffic on the new bridge while half of the truss is being painted, then shifting traffic to allow painting of the rest of the structure.
Advancing completion of the new bridge was considered the best option after the load limit on the existing bridge had to be reduced to 3 tons in January 2012. The load limit restricts the aging structure to vehicles no larger than passenger vehicles and unloaded standard pickup trucks. Eliminating truck traffic from the existing structure has created a hardship for area businesses and farmers.
"I know the 3-ton load limit has created issues for area businesses by rerouting truck traffic and other large vehicles," LeFevre said. "We've continued to make necessary repairs and conduct regular inspections to assure the bridge can remain open for commuter traffic while work progresses on the new bridge."
Updated information about the Ledbetter Bridge, or changes in the functional status of the existing bridge, will be posted for the public promptly at This site is your source for timely and reliable information about the Ledbetter Bridge.
SurfKY News
Information provided by Keith Todd
Photo provided by SurfKY Graphics your social media marketing partner

LIKE SurfKY on Facebook - Click here to LIKE us now.

© Copyright 2015 SurfKY News Group, Inc. All rights reserved. This material may not be published, broadcast, or rewritten without permission. SurfKY News encourages you to share this story on social media.

Weather Sponsored by

In Other News...

Princeton Police Reports Released

PRINCETON, Ky. (10/13/15) — The Princeton Police Department released the following reports Tuesday, Oct. 13. Joseph D.… Read More

Most Read This Week

October 10, 2015 6826

25-Mile Car Chase on Pennyrile Ends in Two Arrests

by SurfKY News
October 07, 2015 5169

Alleged Attempt to Hide Meth in Doughnuts Results…

by SurfKY News
October 07, 2015 3551

3 From Greenville Indicted On Drug Charges

by SurfKY News
October 12, 2015 3551

Crime Stoppers Top Most Wanted - October 12, 2015

by SurfKY News
October 07, 2015 3470

Vehicle Overturns during Two-Car Collision

by Rita Dukes Smith, SurfKY News Director

Most Read This Month

September 16, 2015 14022

Mining Accident Fatality - Update

by Doreen Dennis, SurfKY News
September 30, 2015 12111

Dawson Woman Dead After Princeton Factory…

by SurfKY News

Stories Trending Now

October 12, 2015 3551

Crime Stoppers Top Most Wanted - October 12, 2015

by SurfKY News
October 12, 2015 2366

Two-Vehicle Collision Results in One Driver…

by SurfKY News
October 12, 2015 2267

Four Injured after Vehicle Careens down…

by SurfKY News
October 12, 2015 2255

MPD Foot Patrol Charges Man with Trafficking in…

by SurfKY News
October 13, 2015 2186

Man Accused of Pretending to Hold Gun on Police

by SurfKY News
October 12, 2015 1714

Kentucky Health Co-op Closing Due to Congress…

by SurfKY News
October 12, 2015 1625

Driver Dies after Single-Vehicle Collision on…

by SurfKY News
October 13, 2015 1500

BBQ Champs Chosen during Hanson Lions Blast-off

by Tammy Holloway, SurfKY News
October 12, 2015 1497

UPDATE: KSP Captures Escapee

by SurfKY News
October 12, 2015 1266

Madisonville Police Arrest Reports Released -…

by SurfKY News