ky state TN bridge 300PADUCAH, Ky. (3/19/13) – The contractor for the new U.S. 60 Tennessee River Bridge at Ledbetter had mixed news for the Kentucky Transportation Cabinet (KYTC) this week.
 
KYTC District 1 Chief Engineer Jim LeFevre says while the new bridge is still on track to open well ahead of the original schedule, it will not likely be ready for two-lane traffic in May or June.
 
“The more likely time frame for opening the bridge is mid-summer,” LeFevre said. “Our contractor continues to be committed to getting traffic on the new bridge as quickly as possible. Workers have already starting placing forms to prepare for pouring a deck on the main truss span.”
 
The updated timetable came in the form of a regular progress report from the contractor. LeFevre noted that while work is ahead of schedule on the approach spans, progress on the main truss has been slowed by weather and delays in shipments of steel from mills and fabricators in Minnesota and Wisconsin.
 
In May 2012, transportation officials negotiated a $3.8 million incentive package with the contractor, Kay & Kay/Haydon Brothers. The goal was to get the new bridge opened at least to two-way traffic as much as 14 months ahead of schedule to help alleviate traffic restrictions caused by a 3-ton load limit on the existing bridge.
 
Starting May 1, the state will deduct $19,000 per day from the incentive fund until two-lane traffic is established. If traffic is not running on the new bridge by Sept. 1, the contractor will not receive incentive money.
 
LeFevre says the new bridge is still likely to be open to two-lane traffic almost a year ahead of the original schedule.
 
“We’re still on track to get two-lane traffic moving over to the new bridge in mid-summer,” LeFevre said. “That is our ultimate goal, to restore full connectivity for residents of McCracken County and Livingston County that has been disrupted by the 3-ton load limit on the existing bridge.”
 
Even with a mid-summer opening, the contractor can still claim a portion of the $3.8 million in incentives by cutting almost a year off the original July 2014 opening date.
 
Some of the time saved on the project comes from placing 2-lane traffic on the new bridge while half of the truss is being painted, then shifting traffic to allow painting of the rest of the structure.
 
Advancing completion of the new bridge was considered the best option after the load limit on the existing bridge had to be reduced to 3 tons in January 2012. The load limit restricts the aging structure to vehicles no larger than passenger vehicles and unloaded standard pickup trucks. Eliminating truck traffic from the existing structure has created a hardship for area businesses and farmers.
 
"I know the 3-ton load limit has created issues for area businesses by rerouting truck traffic and other large vehicles," LeFevre said. "We've continued to make necessary repairs and conduct regular inspections to assure the bridge can remain open for commuter traffic while work progresses on the new bridge."
 
Updated information about the Ledbetter Bridge, or changes in the functional status of the existing bridge, will be posted for the public promptly at www.facebook.com/kytcdistrict1. This site is your source for timely and reliable information about the Ledbetter Bridge.
 
SurfKY News
Information provided by Keith Todd
Photo provided by SurfKY Graphics

e-max.it: your social media marketing partner

LIKE SurfKY on Facebook - Click here to LIKE us now.

© Copyright 2015 SurfKY News Group, Inc. All rights reserved. This material may not be published, broadcast, or rewritten without permission. SurfKY News encourages you to share this story on social media.

Most Read This Week

May 30, 2015 7253

Study of Virus Attack on Cancer Sees Success

by Julie Heflin
May 28, 2015 6586

Four Charged with Burglary for Entering Elderly…

by SurfKY News
May 28, 2015 2803

Greenville Man Charged with Rockport Robbery,…

by SurfKY News
May 29, 2015 2443

Hopkins County Grand Jury Indictments

by SurfKY News
May 29, 2015 2428

KSP Seeks Public Help in Locating Wanted Man

by SurfKY News

Most Read This Month

May 15, 2015 11354

New Madisonville Business In Full Operation Soon

by Tammy Holloway, SurfKY News
May 23, 2015 9512

Missing 5-Year-Old Boy Found

by Doreen Dennis, SurfKY News

Stories Trending Now

June 02, 2015 1550

Woman Charged with Falsely Reporting Kidnapping

by SurfKY News
June 02, 2015 1492

Two Muhlenberg Women Injured in Collision

by SurfKY News
June 02, 2015 1442

Traffic Signal at Intersection in Downtown…

by Keith Todd
June 02, 2015 1283

Juveniles Accused of Falsely Reporting Masked…

by Rita Dukes Smith, SurfKY News Director
June 01, 2015 1155

Human Relations Coordinator Identifies Possible…

by Tammy Holloway, SurfKY News
June 02, 2015 1153

Hopkins County Misdemeanor Indictments

by SurfKY News
June 02, 2015 968

Pennyrile Soap Box Derby Hosts 34 Competitors

by Tammy Holloway, SurfKY News
June 02, 2015 883

South Main Accident Slows Northbound Traffic

by Doreen Dennis, SurfKY News
June 02, 2015 875

Madisonville Police Arrest Reports Released -…

by SurfKY News
June 01, 2015 547

Community Breaks Ground for First United Bank…

by Doreen Dennis, SurfKY News