blue Bridge3 300OWENSBORO, Ky. (4/16/13) – Prep work for painting the Ohio River “Blue Bridge” in Owensboro will kick off Sunday night, April 21, with the start of overnight closures running Sunday through Thursday.

The contractor is allowed to close the bridge from 8 p.m. to 5 a.m. Sunday through Thursday for rigging work to secure containment tarps that will go up when the main cleaning and painting work starts after Owensboro’s International Bar-B-Que Festival in May.

Kevin McClearn, chief district engineer for Kentucky Transportation Cabinet District 2, in Madisonville, said the contractor has planned an aggressive schedule with two crews.

“Our contractor will be working 10 to 12 hours a day, sometimes 7 days a week, in an effort to complete the main truss in one construction season,” McClearn said. “The contractor will use the overnight closures starting April 21st to place rigging on the bridge and prepare for placement of equipment so work can ramp up as soon as the bridge is closed to all traffic on May 13.”

The decision to close the bridge entirely for a single season, rather than closing one lane at a time over two seasons, was partly in consideration of trucks and farm equipment, which would have been banned with one-lane traffic.

“Closing the Blue Bridge adds about 10 miles to a commute from Reo, Ind., to downtown Owensboro. We know this is going to be an inconvenience for commuters and truck traffic, but enduring a six-month closure of the bridge was deemed the best choice when compared to one-lane, limited traffic for two construction seasons,” McClearn said. “We want everyone to be prepared for the overnight closures starting April 21 and the full closure starting May 13.”

The Blue Bridge – the formal name is the Glover Cary Bridge and the KY 2262 Ohio River Bridge – will be open without lane restrictions the weekend of Owensboro's International Bar-B-Que Festival. However, the contractor can schedule lane restrictions and overnight closures before then to prepare for work to start immediately after the festival.

The painting contract calls for the bridge to be closed to all traffic from about May 13 through Nov. 15. Work on approach spans can be completed from beneath the bridge with only minor traffic disruptions.

Spartan Contracting, LLC, of Ohio, is the prime contractor on the $10,070,000 painting project, which is jointly funded by Kentucky and Indiana.

The Blue Bridge was originally scheduled for painting in 2017. Last Dec. 19, Gov. Steve Beshear announced that the project would be fast-tracked to complement local efforts to redevelop and revitalize Owensboro’s vibrant riverfront.

The Blue Bridge is 4,622 feet long. It connects Ky. Hwy. 2262 and Indiana State Route 161 over the Ohio River at Owensboro. Approximately 8,500 vehicles cross the Ohio River on the Blue Bridge between Kentucky and Indiana in an average day. Trucks account for about 15 percent of that traffic. The structure opened to traffic in September 1940 as a toll bridge. Tolls were discontinued in 1954.

The Blue Bridge is at Ohio River navigation mile point 756.3.

SurfKY News
Information provided by Keith Todd
Photo provided by SurfKY Graphics

LIKE SurfKY on Facebook - Click here to LIKE us now.

© Copyright 2015 SurfKY News Group, Inc. All rights reserved. This material may not be published, broadcast, or rewritten without permission. SurfKY News encourages you to share this story on social media.

Most Read This Week

April 28, 2015 4287

Search for Stolen Vehicle Ends with Woman Charged…

by SurfKY News
April 28, 2015 3441

Man Charged with Stalking Smoke Shop Clerk

by MPD
May 05, 2015 3021

Meth Charge Follows MPD Investigation into…

by SurfKY News
May 05, 2015 2989

School Board Studies Further Spending Cuts

by Charles W. Riley II, SurfKY News
April 30, 2015 2932

Family Says 'Goodbye' to Dog After It Allegedly…

by Doreen Dennis, SurfKY News

Most Read This Month

April 17, 2015 15815

An Open Letter from an Addict

by Olivia Kirks
April 23, 2015 8568

Man Charged with Sodomy, Incest/Victim under 12

by SurfKY News

Stories Trending Now

May 05, 2015 3021

Meth Charge Follows MPD Investigation into…

by SurfKY News
May 05, 2015 2989

School Board Studies Further Spending Cuts

by Charles W. Riley II, SurfKY News
May 05, 2015 1227

First United Bank Becomes Hopkins School System’s…

by Tammy Holloway, SurfKY News
May 05, 2015 1045

Madisonville Man Goes to Hospital after…

by SurfKY News
May 05, 2015 808

Madisonville Police Arrest Reports - May 5, 2015

by SurfKY News
May 05, 2015 790

Two on Moped Injured in Collision with Car

by Doreen Dennis, SurfKY News
May 05, 2015 777

Baptist Health Madisonville Establishes Foundation

by Kristy J. Quinn
May 05, 2015 484

SurfKY Spotlight: First Kentucky Bank

by Gary Gates, SurfKY News
May 05, 2015 418

May 2015 In-House Rabies Clinics' Schedule

by Barry L. Franklin
May 05, 2015 395

Kentucky Lottery Results for Monday May 4, 2015

by Kentucky Lottery