I-69 / I-66 / I-65 Spur Corridor Study Completed

ky trans 300MADISONVILLE, Ky. (6/2/14) — The Kentucky Transportation Cabinet has completed a study of the potential cost of updating the Audubon Parkway, U.S. 60, and the Natcher Parkway to current Interstate highway standards.

Completion of the Interstate 69 corridor, from Fulton to Henderson, is the cabinet’s main focus for Western Kentucky.“The Kentucky Transportation Cabinet remains committed to the completion of I-69 at Henderson, as has been planned for many years,” Kentucky Transportation Secretary Mike Hancock said.

But the study, by Palmer Engineering, of Winchester, Kentucky, explored what it would take to bring an “Interstate Spur” to Owensboro by attaining an “I-69 Spur” designation for the Audubon Parkway or an “I-66/I-65 Spur” designation for the Natcher Parkway.

The consultants evaluated existing conditions along the corridor, including safety and operation considerations; identified Interstate criteria deficiencies and developed cost estimates for improvements to reach Interstate compliance.

KYTC District 2 Chief District Engineer Kevin McClearn says like earlier studies of the Pennyrile Parkway, the Western Kentucky Parkway, and the Purchase Parkway, the report can provide direction for future efforts.

“This study gives an idea of what it would take to bring an ‘Interstate Spur’ to Owensboro,” McClearn said. “While we are still several years away from finishing out projects required for bringing some other parkways up to standards to obtain an I-69 designation, once that effort nears completion we will have this to provide direction for work that could be done along the Audubon or the Natcher Parkways, which already have official spur corridor status.”

The lengthy study presented a number of findings.

A list of identified deficiencies along the routes include:

  • Previous Toll Plaza Interchanges

  • Vertical alignment

  • Ramp length

  • Interchange spacing

  • Overpass clearance

  • Merge area length at interchanges

  • Bridge width

The consultant looked at three possible approaches, including a “no-build” option. The study also examined necessary upgrades and spot safety improvements, some of which would require the Federal Highway Administration to approve design exceptions and, finally, a fully compliant reconstruction addressing all issues without the need for exceptions or variances from FHWA.

Cost estimates in the study were expressed in today’s dollars. Measurably higher estimates could be expected by the time of construction.

For the 23.4 miles of the Audubon from Henderson to the U.S. 60 Interchange at Owensboro, it is estimated to cost $14 million to $15 million for basic upgrades required to attain an I-69 Spur designation. That is dependent on the Pennyrile Parkway being successfully upgraded to I-69 status on the west end of the Audubon and does not include any cost associated with rebuilding the Audubon/Pennyrile Parkway Interchange at Henderson.

Upgrading 72.2 miles of the Natcher Parkway from I-65 at Bowling Green to U.S. 60 at Owensboro to attain an I-65 Spur designation is estimated to cost $66 million to $76 million

Improvements to the Audubon and U.S. 60 to the Natcher Interchange at Owensboro are estimated at $66 million to $87 million – due in part to the necessity of reworking the Audubon/U.S. 60 Interchange at Owensboro, which would be costly.

The last option included 6.65 miles of U.S. 60 around Owensboro and 72.2 miles of the Natcher from Owensboro to Bowling Green. That was estimated to cost $117 million to $148 million, with upgrades to the Natcher/U.S. 60 Interchange a major part of that cost.

The consultant did not recommend trying to designate U.S. 60 as a spur. “The existing U.S. 60 and Natcher Parkway interchange is surrounded by residential development which will be greatly impacted with the necessary improvements to the interchange and U.S. 60 to meet interstate criteria,” the study said. “… It may be cost prohibitive to designate U.S. 60 as I-66/I-65 Spur of I-69 Spur.”

At the request of the Transportation Cabinet, the consultant added a separate review of U.S. 60 and U.S. 231 from the Natcher Parkway Interchange to the William Natcher Bridge as a change order to the spur studies. That study is also completed and placed on the KYTC website as a separate report.

The consultant found the William Natcher Bridge, which started carrying U.S. 231 traffic across the Ohio River in 2002, already meets minimum Interstate standards. However, the study noted there is a heavy cost to making 10.8 miles of U.S. 60 and 3.5 miles of U.S. 231 Interstate compliant from the Natcher Parkway to the bridge.

In a briefing to the Owensboro Regional Chamber of Commerce Executive Board Thursday, McClearn, and Gary Sharpe, of Palmer Engineering, indicated that the cost for upgrading a 14.3-mile section of U.S. 60 and U.S. 231 from the Natcher Parkway Interchange to the Ohio River is estimated at $150 million to $250 million. The released study approximates it at $177 million. The greater cost per mile is due to intermittent, uncontrolled access points along the roadway. Such access is prohibited on Interstates.

McClearn noted a new interchange would be required at the intersection of U.S. 60 and U.S. 231 near the Bridge, adding substantial costs. Additionally, a heavy network of frontage roads would be required for affected businesses and residences due to the removal of direct access to the highway between the Natcher Parkway and the bridge.

Left completely unanswered – being outside the scope of the study – is the question of what would have to happen on the other side of the Ohio River.

Indiana, which is heavily invested in building I-69 from Evansville to Bloomington, would have to be willing to upgrade 22 miles of U.S. 231 from the William Natcher Bridge to I-64.

The study also noted that while the I-69 Spur and I-65 Spur are congressionally recognized as FHWA Corridors in Federal Law, the much talked about I-67 is not.

The I69/I-65 Spur Study has been posted to the KYTC website at http://transportation.ky.gov/Planning/Pages/Project-Details.aspx?Project=I-69, I-66/I-65 Spurs and US 60 Connection Strategic Planning Corridor Study. The I-67 Overview is available at http://transportation.ky.gov/Planning/Pages/Project-Details.aspx?Project=I-67 Corridor Overview.

SurfKY News
Information provided by Keith Todd

© Copyright 2015 SurfKY News Group, Inc. All rights reserved. This material may not be published, broadcast, or rewritten without permission. SurfKY News encourages you to share this story by using one of the social media links below.

3/13 - 16
button coupons
3/13 - 16
3/13 - 16
button classifieds

In Other News...

School Board Hears Public Comments Regarding Proposed Utility Tax

GREENVILLE, Ky. (1/22/15) ― The Muhlenberg County School Board held a public hearing Jan. 22 to listen to comments on a… Read More

MCCH Offers Free Screenings at the Love Your Heart Health Screening Event on Feb. 6

MURRAY, Ky. (1/25/15) — Murray-Calloway County Hospital encourages you to Love Your Heart in recognition of American… Read More
3/13 - 16

Most Read This Week

January 19, 2015 9062

Two-Year-Old Child Dies after Being Struck by…

in Top News For All Sites by Paul Ray
January 19, 2015 8924

UPDATE - Lady Mustangs Fall to South Warren

in Local (Muhlenberg) Top News by Steve LeMaster
January 23, 2015 7766

Local Church's Faith Restored; 71 Souls Saved…

in Video by Gary Gates, SurfKY News
January 22, 2015 6849

Nortonville Man Accused of Selling Drugs near…

in Local (Hopkins) Top News by Madisonville Police Department/Hopkins County Jail
January 20, 2015 6746

Bridal, Prom, Pageant Expo Planned for February…

in Hopkins News by Dana Brown
January 23, 2015 5440

Parents Face Charges after Marijuana Joint Falls…

in Local (Hopkins) Top News by Madisonville Police Department/Hopkins County Jail
January 21, 2015 5378

KYDOT Pre-Treating Roads Thursday in Antipation…

in Top News For All Sites by Keith Todd
January 22, 2015 4855

MCEA Head: Further School Mergers Might Ease…

in Local (Muhlenberg) Top News by Paul McRee, SurfKY News
January 21, 2015 4724

Man Arrested after Allegedly Nodding off on Baby…

in Local (Hopkins) Top News by Madisonville Police Department/Hopkins County Jail
January 18, 2015 4415

Single Vehicle Injury Collision On Cleaton Road

in Local (Muhlenberg) Top News by Stu Recke, KSP

Stories Trending Today

January 25, 2015 2925

Dean’s List Announced

in Top News For All Sites Touching Hopkins by Joyce Riggs
January 23, 2015 2378

School Board Hears Public Comments Regarding…

in Local (Muhlenberg) Top News by Charles W. Riley II, SurfKY News
January 24, 2015 1954

Five Injured in Two-Vehicle Collision

in Local (Muhlenberg) Top News by Chris E. King
January 24, 2015 1627

PSC Bars $54 Million in Kentucky Power Fuel Cost…

in General News For All Sites by Andrew Melnykovych
January 25, 2015 1586

UPDATE: Two Die, Two Injured in Two-Vehicle…

in Local (Owensboro) Top News by Dispatcher Dustin Staves
January 24, 2015 1585

Happenings, Meetings Listed for Hopkins County

in Hopkins News by Amber Averitt, SurfKY News
January 24, 2015 1573

Kentucky 2014 Highway Fatality Figures Released

in General News For All Sites by Keith Todd
January 24, 2015 1473

Keeping the Faith - 'What It's Good For'

in General News For All Sites by Ronnie McBrayer
January 24, 2015 1406

Busting the Myths of Leadership

in General News For All Sites by David Taylor
January 24, 2015 1280

Hooked on Science - Feather Balance

in General News For All Sites by Jason Lindsey

SurfKY News Group, Inc.
Corporate Office & Studio
1125 Nebo Rd.  •  Madisonville, KY 42431
270.452.2727 (phone)
  •  270.452.2249 (fax)


Contact a member of our staff: www.surfky.com/contact
Copyright © 2015 SurfKY News Group, Inc.  •  Terms of Use  •  Site Map

social fbsocial twsocial yt
social gpsocial flr subscribevideoitunessocial rss